Challenges

The passage of the utility pipe at a shallow depth and the possibility of problems due to rolling

Solution

Implementation of concrete blocking instead of earth foundation and implementation of polymer asphalt layer instead of two layers of simple asphalt

EmployerIsfahan Municipality
ContractorIsfahan Municipal Civil Organization
Implementation dateSummer of 2021
The length of the polymer asphalt road2500 m
Thickness reduction20 %
The amount of economic savings in construction costs3,500,000,000Rial
The location of the project implementation siteIsfahan city, Khatunabadi highway, Moqdad II street